Non-Town Utility Work

Hartwell Rd: South Rd to #180 Hartwell Road

Eversource will be constructing new underground electric conduits to replace older ones. They will be delivering notices to abutters and putting up electronic message boards.

The work will take place starting Nov 18, 2024 and be substantially complete in March, 2025.  The Town is currently waiting on updates regarding final completion of the project.

Eversource will be required to keep Hartwell Rd open, with one-way alternating traffic which will lead to some delays. Please use alternative routes or give yourself extra time when traveling.

To help facilitate curbside trash and recycling services, residents should have carts at the curbside by 6AM. The Town’s collection contractor will prioritize early collection to minimize any possible collection issues or delays.

Any questions about the project please contact Eversource at: