Projects

CURRENT Projects

  • Bedford Police Station Addition and Renovations: Construction in process, anticipated completion Spring/Summer 2023
  • Bedford Fire Station HVAC Replacement:  Equipment has been ordered, pending delivery and installation
  • Bedford Public Library Elevator Control Upgrades: Equipment ordered, anticipated completion Spring 2023
  • Police Station Elevator Control Upgrade: Equipment ordered, anticipated completion Spring 2023
  • Lane School Elevator Control Upgrade: Equipment ordered, anticipated completion Summer 2023

 

FUTURE Projects

  • Bedford Public Library HVAC Renovation Project:   Project is in the design phase with bidding to be completed spring 2023; construction summer 2023 through Spring 2024
  • New Bedford Fire Station:   Designer to be selected Spring 2023, anticipating construction to start Spring 2024
  • Depot Station: Painting and deck replacement  Work bid out, and anticipated to begin Spring 2023
  • Sabourin Restrooms:  In the Design phase, anticipating construction Summer 2023